Demolition

Timeline

Date

Event

1972

Waterloo Incinerator commences operation

1997

Waterloo Incinerator closed

April 2006

City of Sydney adopts new planning controls for the Green Square Town Centre

December 2006

The Green Square Town Centre Local Environmental Plan (LEP) is gazetted

January 2007

Waverley and Woollahra Councils resolve to sell the Waterloo Incinerator site to Landcom

January 2007

Landcom begins meeting with local residents to talk about our plan to demolish the Incinerator

February 2007

Planning for demolition
Consultation with local residents

March / April 2007

Detailed planning for demolition
First newsletter distributed

July 2007

Demolition application to be lodged with City of Sydney.

August 2007

Second newsletter distributed
Landcom host community sessions for residents to talk about demolition of the Incinerator.

October 2007

Development Application to demolish Waterloo Incinerator approved by the City of Sydney.

November 2007

Landcom awarded the contract for the demolition to Metrpolitan Demolitions Group.

December 2007

Demolition to commence
Third newsletter distributed

March 2008

4th newsletter distributed

2008/09

First development of Green Square Town Centre expected to commence